BMW 7_aya the E38 series from 1994 to 2002
1. Introduction
2. Governing bodies and methods of operation
3. Settings and routine maintenance of the car
4. Engine
4.1. General information and preparatory operations
4.2. Check of compression pressure
4.3. Check of the engine by means of the vacuum gage
4.4. Petrol M60/1 and M60/2 engines
4.4.1. Removal and installation of a cover of a head of cylinders
4.4.2. Removal and installation of a head of cylinders, adjustment of phases GRM
4.4.3. Removal and installation of the top section of the pallet of a case
4.4.4. Removal and installation of the pallet of a case
4.4.5. Removal and installation of covers of a chain of GRM
4.4.6. Replacement of epiploons of a bent shaft
4.4.7. Removal and installation of a flywheel
4.4.8. Removal and installation of belts of the drive of auxiliary units
4.4.9. Removal and installation of a damper of tortional fluctuations and its nave
4.4.10. Removal and installation of the oil pump
4.4.11. Removal and installation of the inlet pipeline
4.4.12. Removal and installation of final collectors
4.4.13. Removal and installation of the engine
4.5. M62 engine
4.6. Diesel M57 engine
4.7. Diesel M67 engine
5. Cooling systems of the engine, heating, ventilation and air conditioning
6. A power supply system and production of the fulfilled gases
7. Systems of electric equipment of the engine
8. Manual box of gear shifting and coupling
9. Automatic transmission
10. Cardan and power shafts, reducer, differential and stupichny assemblies
11. Brake system
12. Suspension bracket and steering
13. Body
14. Onboard electric equipment
15. Schemes of electric equipment


Факторы риска заражения геморроем налицо


4-4-13-snyatie-i-ustanovka-dvigatelya.html

4.4.13. Removal and installation of the engine

 PERFORMANCE ORDER

  1. Perform the operations described in paragraphs with 1 on 4 Sections Removal and installation of the top section of the pallet of a case.
  2. Remove the lower part of the air cleaner.
  3. Disconnect the union of the vacuum line from the amplifier of brakes (see an illustration).
  1. Turn out bolts of fastening of a full-line oil filter and hang out it on the engine, without disconnecting pipelines.
  1. Disconnect the bringing and returnable fuel hoses from the fuel distributive highway.
  1. If necessary disconnect an air hose (2) from the one-pass valve of system of decrease in toxicity of OG.
  1. Disconnect cables of management from a butterfly valve.
  1. Separate the socket (2) and disconnect a vacuum hose (3) from the EVAP system valve.
  1. Separate the socket of an electrical wiring of the engine and take an electrical wiring plait aside.
  2. Unclench a bracket of fastening of the diagnostic socket and hang out the socket.
  3. Remove the left and right thermofilters.
  4. Turn out drain traffic jams of cooling liquid on the left and right parties of the block of cylinders.
  5. Remove a cooling system radiator (see the Head of the Cooling system of the engine, heating, ventilation and conditioning.
  6. Remove RKPP or AT (see the Section Removal and installation of the top section of the pallet of a case or Removal and installation of the pallet of a case).
  7. Disconnect a positive wire of the rechargeable battery from a starter and remove a starter (see the Head Sistemy of electric equipment of the engine).
  8. Disconnect positive wires of the rechargeable battery from a case, pillows of the left arm and from the generator.
  9. Remove a branch pipe of an obduv of the generator (see an illustration).
  10. Take off a generator drive belt (see the Section Removal and installation of belts of the drive of auxiliary units), the pump GUR and a belt of the drive of the K/V compressor (see the Section Removal and installation of belts of the drive of auxiliary units).
  11. Disconnect the K/V compressor from a basic arm and suspend the compressor aside, without disconnecting from it a tube.
  1. Disconnect a weight wire from the right support of the engine and turn out the top nuts of the left and right pillows of support of the engine.
  1. Disconnect hoses from a cooling system collector.
  1. Remove final collectors (see the Section Removal and installation of final collectors).
  2. By means of the special lifting device take the engine from a motive compartment, having lifted it for forward and back lifting eyes (see illustrations).

Do not damage components in a motive compartment during raising of the engine.

  1. Installation is made in the sequence, the return to an order of dismantle of components. Be convinced of integrity of pillows of support and if necessary replace them.
  2. After installation before start of the engine check levels of working liquids and if necessary modify them.
  3. Start the engine and make sure of lack of leak of fuel and working liquids, and also of lack of abnormal noise and vibrations.
  4. Let's the engine work on single turns, then muffle it and again check levels of working liquids.


"previous page
4.4.12. Removal and installation of final collectors
following page"
4.5. M62 engine