BMW 7_aya the E38 series from 1994 to 2002
1. Introduction
2. Governing bodies and methods of operation
3. Settings and routine maintenance of the car
4. Engine
4.1. General information and preparatory operations
4.2. Check of compression pressure
4.3. Check of the engine by means of the vacuum gage
4.4. Petrol M60/1 and M60/2 engines
4.5. M62 engine
4.5.1. Removal and installation of covers of heads of cylinders
4.5.2. Removal and installation of heads of the block of cylinders
4.5.3. Removal and installation of the top section of the pallet of a case and oil pump
4.5.4. Removal and installation of the pallet of a case
4.5.5. Removal and installation of covers of a chain of GRM
4.5.6. Replacement of epiploons of a bent shaft and consolidations of distributors of ignition
4.5.7. Removal and installation of a flywheel
4.5.8. Removal and installation of a damper of tortional fluctuations
4.5.9. Removal and installation of driving belts
4.5.10. Removal and installation of the oil pump
4.5.11. Removal and installation of inlet pipelines
4.5.12. Removal and installation of final collectors
4.5.13. Removal and installation of the engine
4.6. Diesel M57 engine
4.7. Diesel M67 engine
5. Cooling systems of the engine, heating, ventilation and air conditioning
6. A power supply system and production of the fulfilled gases
7. Systems of electric equipment of the engine
8. Manual box of gear shifting and coupling
9. Automatic transmission
10. Cardan and power shafts, reducer, differential and stupichny assemblies
11. Brake system
12. Suspension bracket and steering
13. Body
14. Onboard electric equipment
15. Schemes of electric equipment


Как выбрать новый автомобиль


4-5-11-snyatie-i-ustanovka-vpusknykh-truboprovodov.html

4.5.11. Removal and installation of inlet pipelines

The description for the inlet pipeline of cylinders No. No. 1-6 is given below. Removal and installation of the inlet pipeline of cylinders No. No. 7-12 is made similarly.


 PERFORMANCE ORDER

  1. Remove the fuel distributive highway assembled with injectors.
  1. Separate the socket (1). Turn out bolts of fastening of the case of a butterfly valve, remove it, without disconnecting hoses, and take aside.

At installation replace laying between the pipeline and the case of a butterfly valve.


  1. Note laying of wires of sensors of a detonation (1 and 2) on the inlet pipeline.
  1. Turn out bolts of fastening of a noise-insulating slip and remove it.
  1. Give nuts and take aside high-voltage wires.
  1. Turn out bolts of fastening of the inlet pipeline by means of adaptation (nozzle) No. 11 6 060.
  1. Turn out bolts (1) of fastening of the adjusting valve of system of ventilation of a case of the engine (PCV) and remove it.
  1. If necessary pick up the ventilating phone (1).

Pay attention to the adjusting provision of a ventilating tube (1) in a collector (2).

  1. Installation is made upside-down.